The 121 Anglesea Street development in Hamilton shows how coordinated geotechnical and environmental engineering can reduce uncertainty, simplify delivery and keep a complex brownfield project moving.
Understanding the site before construction
The development is being delivered by Livingstone Building Limited on a constrained commercial site with a history that included service station and motor vehicle workshop activities. Before construction could progress, the project team needed a reliable understanding of both the ground conditions and the site’s environmental legacy.
GWE completed a two-stage geotechnical investigation using our Hilux-mounted Ground Master drill rig, supported by Cone Penetration Testing undertaken by others. Staging the investigation allowed the team to refine the scope as new information became available and focus additional work where it would provide the greatest value.

Practical design built around construction
Our involvement continued beyond the investigation. GWE completed sheet pile design and crane platform design, translating the ground model into practical temporary works solutions for a constrained urban construction site.
As works progressed, our engineers also completed inspections of foundation preparation and site rehabilitation. Remaining involved during construction meant conditions could be verified as they were exposed, with timely advice available to the contractor and wider project team.
Managing the environmental legacy
The site’s former use had left residual petroleum hydrocarbons beneath part of the proposed building platform, creating a potential vapour pathway and a consenting and human-health risk.
GWE delivered the contaminated-land programme from investigation through to validation, including a Preliminary Site Investigation, Detailed Site Investigation, Remedial Action Plan, construction monitoring and Site Validation Report.
Approximately 120 cubic metres of impacted soil was excavated from the remedial area. Eighteen validation samples were analysed for petroleum-related contaminants, and approximately 452 cubic metres of imported GAP 40 and clean fill was documented. Validation confirmed that the remediation objectives had been achieved, and the vapour pathway had been mitigated to an acceptable level for future occupants.
The value of one coordinated team
121 Anglesea Street development is not defined by one technical service. Its value as a case study lies in the way geotechnical investigation, temporary works design, contaminated-land remediation and construction support were connected across the project lifecycle.
For the client and contractor, that continuity meant fewer gaps between disciplines, faster access to people who already understood the site,
Complex projects become easier to deliver when investigation, design, remediation and construction support are connected.
It is a practical example of how GWE Waikato helps turn complex site constraints into a coordinated pathway forward.